Construction Management (GPSC Civil PYQs) Test 1 (Free)

Report a question

You cannot submit an empty report. Please add some details.
0 votes, 0 avg
2

Construction Management (GPSC Civil PYQs) Online Test 1 (Free)

-: Symbols & Description :-

(નિશાનીઓ અને તેનું વર્ણન)

 

-: Instructions :-

(સૂચનાઓ)

 

1. Click On Full Screen Mode (¤) From Corner For Best Test Experience

(બેસ્ટ ટેસ્ટ અનુભવ માટે ખૂણામાં આપેલ ફૂલ સ્ક્રીન મોડ (¤) ઉપર ક્લિક કરો)

2. Use Navigation Bar For Jumping Forward or Backward To Any Question

(કોઈ પણ પ્રશ્ન ઉપર જવા માટે નેવિગેશન બારનો ઉપયોગ કરવો)

3. Submit Test Button Will Be Only Visible At The Last Question

(ટેસ્ટ સબમિટ કરવાનો ઓપ્શન માત્ર છેલ્લા પ્રશ્ન ઉપર હશે)

4. Don't Forget To Give Your Rating & Review At The End Of Test

(ટેસ્ટ પૂરી થયા પછી રેટિંગ & રિવ્યુ આપવાનું ભુલશો નહીં)

 

"BEST OF LUCK"

[Click On Full Screen Mode (¤) From Corner For Best Test Experience]

(બેસ્ટ ટેસ્ટ અનુભવ માટે ખૂણામાં આપેલ ફૂલ સ્ક્રીન મોડ (¤) ઉપર ક્લિક કરો)

---------------

Your Name

1 / 10

Category: Construction Management (GPSC Civil PYQs)

For a given load rating, the operating radius of crane can be increased by

(i) increasing the length of arm

(ii) increasing the horse power

2 / 10

Category: Construction Management (GPSC Civil PYQs)

One of the following is not a earth excavation and lifting equipment

3 / 10

Category: Construction Management (GPSC Civil PYQs)

The problem of developing low-cost housing for economically backward people in undeveloped region should be analyzed by

4 / 10

Category: Construction Management (GPSC Civil PYQs)

Which statement is incorrect?

5 / 10

Category: Construction Management (GPSC Civil PYQs)

Figure below shows the network for a particular project which consists of four activities.

Normal time and crash time for each activity are given below

The minimum time required for the completion of project is _________

6 / 10

Category: Construction Management (GPSC Civil PYQs)

The minimum time that the project will take for its completion will be the sum of the crashed time duration of __________

7 / 10

Category: Construction Management (GPSC Civil PYQs)

The order of booking dimensions is

8 / 10

Category: Construction Management (GPSC Civil PYQs)

The probability distribution taken to represent the completion time in PERT analysis is

9 / 10

Category: Construction Management (GPSC Civil PYQs)

In PERT technique, completion of an activity is called

10 / 10

Category: Construction Management (GPSC Civil PYQs)

If the Optimistic time, the most probable estimate and the pessimistic time for a given activity are 7, 10 and 19 days respectively then the ‘expected time’ for this activity will be _________ days ?

Your score is

The average score is 50%

0%

"Rate This Test"

"Thank You"

Leaderboard
Pos.NameScoreDuration
1Sudhanshu70 %4 minutes 59 seconds
2Jaydip30 %1 minutes 53 seconds
Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments