100+ Free Surveying MCQs, Civil Engineering MCQs

Surveying MCQs

Surveying MCQs


The included angles of a theodolite traverse, are generally measured

A) clockwise from the forward station

B) anti-clockwise from the back station

C) anti-clockwise from the forward station

D) clockwise from the back station

Check Answer

D) clockwise from the back station


The line normal to the plumb line is known as

A) horizontal line

B) level line

C) datum line

D) vertical line

Check Answer

B) level line


The angle of intersection of a curve is the angle between

A) back tangent and forward tangent

B) prolongation of back tangent and forward tangent

C) forward tangent and long chord

D) back tangent and long chord

Check Answer

A) back tangent and forward tangent


The additional lines which are measured to show the correctness of the chain surveying are called:

A) check clines

B) proof lines

C) tie lines

D) all of these

Check Answer

D) all of these


Locating the position of a plane table station with reference to three known points, is known as

A) intersection method

B) radiation method

C) resection method

D) three point problem

Check Answer

D) three point problem


Chain surveying is well adopted for

A) small areas in open ground

B) small areas with crowded details

C) large areas with simple details

D) large areas with difficult details

Check Answer

A) small areas in open ground


Subtense tacheometry is generally preferred to if ground is

A) flat

B) undulating

C) mountaineous

D) deserts

Check Answer

B) undulating


For high sensivity of the bubble tube

A) a liquid of low viscosity is used

B) a liquid of low surface tension is used

C) the bubble space should be long

D) all the above

Check Answer

D) all the above


Short offsets are measured with

A) an ordinary chain

B) an invar tape

C) a metallic tape

D) a steel tape

Check Answer

A) an ordinary chain


Check lines (or proof lines) in Chain Surveying, are essentially required

A) to plot the chain lines

B) to plot the offsets

C) to indicate the accuracy of the survey work

D) to increase the out-turn

Check Answer

C) to indicate the accuracy of the survey work