The expected out turn of 12 mm plastering with cement mortar is |
A) 2.5 sq m
B) 8.0 sq m
C) 6.0 sq m
D) 4.0 sq m
The total length of a cranked bar through a distance (d) at 45° in case of a beam of effective length L, is |
A) L + 0.42 d
B) L + 2 x 0.42 d
C) L – 0.42 d
D) L – 2 x 0.4 d
Which method is useful in case of buildings which several similar bays? |
A) Typical bay method
B) Cubical content method
C) Percentage method
D) Cost comparison method
IS code for mode of measurement is |
A) IS : 1200
B) IS : 2100
C) IS : 12100
D) IS : 21100
Pick up the item of work not included in the plinth area estimate |
A) Wall thickness
B) Room area
C) Verandah area
D) Courtyard area
In a detailed estimate the provision for work charged establishment charges is usually |
A) 3 to 5 %
B) 5 to 7%
C) 2 to 2.5 %
D) Above 10%
For items like water supply fittings, sanitary fittings, door and window fittings, etc. a lump sum amount is put up in the bill of quantities. This amount is known as |
A) Prime Cost
B) Provisional sum
C) Spot item
D) Day work
The brick work is measured in sq metre, in case of |
A) Honey comb brick work
B) Brick flat soling
C) Half brick walls or the partition
D) All the above
The excavation exceeding 1.5 m in width and 10 sq.m in plan area with a depth not exceeding 30 cm, is termed as |
A) Surface excavation
B) Cutting
C) Surface dressing
D) Excavation
The expected out turn of cement concrete 1 : 2 : 4 per mason per day is |
A) 1.5 m3
B) 3.5 m3
C) 5.0 m3
D) 2.5 m3