Estimating, Costing and Valuation Mcqs

Practice Quiz on Estimating, Costing and Valuation Mcqs

30 Marks

1 / 30

The expected out turn of cement concrete 1 : 2 : 4 per mason per day is

2 / 30

While mixing cement mortar by volume, the volumn of cement bag is specified as

3 / 30

In specification of earthwork in foundation, lift and lead specified are, respectively

4 / 30

The expected task work for earthwork in excavation in ordinary soil per mazdoor per day is

5 / 30

The total length of a cranked bar through a distance (d) at 45° in case of a beam of effective length L, is

6 / 30

In a detailed estimate the provision for work charged establishment charges is usually

7 / 30

The cost under item of work is calculated from the quantities already computed at workable rate, and the total cost is worked out in a prescribed form known as

8 / 30

Pick up the item of work not included in the plinth area estimate

9 / 30

How many kilogram binding wire is required for 1570 kg steel?

10 / 30

In which method it is assumed that the property loses its value by the same amount every year.

11 / 30

Capitalized value =

12 / 30

The excavation exceeding 1.5 m in width and 10 sq.m in plan area with a depth not exceeding 30 cm, is termed as

13 / 30

Volume of sand carried in a truck is approximately

14 / 30

The owner of a property can borrow money against the security of his property. Such advancement of money against any form of security is called as

15 / 30

Which specification is not a part of the contract document?

16 / 30

Which estimate is least accurate?

17 / 30

For items like water supply fittings, sanitary fittings, door and window fittings, etc. a lump sum amount is put up in the bill of quantities. This amount is known as

18 / 30

The expected out turn of 12 mm plastering with cement mortar is

19 / 30

In sinking fund, depreciation =

20 / 30

‌‌‌‌‌‌‌__________ is the net instalment of annual or periodical payment for repayment of the capital amount invested in a property for a specified period.

21 / 30

The scrap value of a building is usually taken as ________ of the total cost of construction.

22 / 30

The property which can not be moved from one place to another place, is called

23 / 30

In the specification, cement shall be used as per

24 / 30

The brick work is measured in sq metre, in case of

25 / 30

IS code for mode of measurement is

26 / 30

______________ include general office expenses, rents, taxes, supervision and other costs which are indirect expenses and not productive expenses on the job.

27 / 30

Cross-section of earthwork of road in banking is in the form of trapezium. Name the method to calculate the quantity of earthwork.

28 / 30

Which method is useful in case of buildings which several similar bays?

29 / 30

The value of a property that can be obtained at any particular time from the open market it the property is put for sale, is called

30 / 30

Extreme cold, heat or rain may

Your score is

0%


The expected out turn of 12 mm plastering with cement mortar is

A) 2.5 sq m

B) 8.0 sq m

C) 6.0 sq m

D) 4.0 sq m

B) 8.0 sq m


The total length of a cranked bar through a distance (d) at 45° in case of a beam of effective length L, is

A) L + 0.42 d

B) L + 2 x 0.42 d

C) L – 0.42 d

D) L – 2 x 0.4 d

B) L + 2 x 0.42 d



Which method is useful in case of buildings which several similar bays?

A) Typical bay method

B) Cubical content method

C) Percentage method

D) Cost comparison method

A) Typical bay method


IS code for mode of measurement is

A) IS : 1200

B) IS : 2100

C) IS : 12100

D) IS : 21100

A) IS : 1200



Pick up the item of work not included in the plinth area estimate

A) Wall thickness

B) Room area

C) Verandah area

D) Courtyard area

D) Courtyard area


In a detailed estimate the provision for work charged establishment charges is usually

A) 3 to 5 %

B) 5 to 7%

C) 2 to 2.5 %

D) Above 10%

C) 2 to 2.5 %



For items like water supply fittings, sanitary fittings, door and window fittings, etc. a lump sum amount is put up in the bill of quantities. This amount is known as

A) Prime Cost

B) Provisional sum

C) Spot item

D) Day work

A) Prime Cost


The brick work is measured in sq metre, in case of

A) Honey comb brick work

B) Brick flat soling

C) Half brick walls or the partition

D) All the above

D) All the above



The excavation exceeding 1.5 m in width and 10 sq.m in plan area with a depth not exceeding 30 cm, is termed as

A) Surface excavation

B) Cutting

C) Surface dressing

D) Excavation

A) Surface excavation


The expected out turn of cement concrete 1 : 2 : 4 per mason per day is

A) 1.5 m3

B) 3.5 m3

C) 5.0 m3

D) 2.5 m3

C) 5.0 m3


Click Here to View All Civil Engineering Mcqs With Practice Quiz
Join Our Telegram Group For Daily Civil Engineering Practice Quiz
Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments