Here You will find ‘Building Information Modeling MCQ Questions Answers’. All MCQs are free to practice. We provided all answers below every MCQs, so you can check your answer. Keep visiting our website. We also provide study materials, MCQs practice and test series related to the various competitive exams. We also provide latest government job information.
Building Information Modeling MCQ (1-5)
a combined Building Information Model that has been compiled by amalgamating several different models into one, is called ______.
- Federated model
- Government Soft Landings
- Industry Foundation Class
- Information Delivery Manual
Check Answer
Federated model
Which of the following information can be generated through BIM?
- Quantities
- Schedule
- Operations
- All of the above
Check Answer
All of the above
What is BIM?
- A way of designing buildings
- A project management technique
- A type of software
- A way of managing building information
Check Answer
A way of managing building information
Which of the following modeling can be done through BIM?
- MEP System
- Sustainability
- Management
- All of the above
Check Answer
All of the above
What is the benefit of using BIM technology for designers, engineers, and architects?
- It is a cheaper alternative to other design software
- It is not as widely used as other design software
- They are able to see their upcoming projects in 3D
- BIM only allows for 2D design
Check Answer
They are able to see their upcoming projects in 3D
Building Information Modeling MCQ (6-10)
What is the foundation for building design, construction, and operations optimization?
- Estimating
- Building Information Modeling
- Scheduling
- Project Management
Check Answer
Building Information Modeling
To gain the most benefits from BIM, it is customary to involve as many ______ as possible in the early design stages.
- customers
- financial institutions
- stakeholders
- office of the AIA
Check Answer
stakeholders
Building + Information + Modelling = ?
- Process + People + Platform
- management + people +organisation
- work permit + health and safety + management
- platform + management + software
Check Answer
Process + People + Platform
Which of the following is not an element of BIM?
- Technologies
- Tendering
- Processes
- Policies
Check Answer
Tendering
What are the advantages of 3D BIM ?
- Streamlined sharing of design expectations and communication
- Enhanced 3D visualization of the entire project
- Reduced rework and revisions because there was total transparency from the start
- All of the above
Check Answer
All of the above
Building Information Modeling MCQ (11-15)
What is the Building Information Model (BIM) ?
- BIM process transforms analog information into a digital model.
- BIM process transits analog information into a digital model.
- BIM process transforms digital information into an analog model.
- BIM process transforms analog information into a digital model.
Check Answer
BIM process transforms analog information into a digital model.
Which of the following Modeling can not be done through BIM?
- Site
- Website
- Architectural
- Structural
Check Answer
Website
Which of the following is an use of BIM in project life cycle?
- Management of BIM models
- BIM in construction management
- BIM in facility operation
- All of the above
Check Answer
All of the above
Which of the following is not a future potential of BIM?
- Improved Productivity
- Improved Speed of delivery
- Improved Coordination
- Reduced Enviromental Impact
Check Answer
Reduced Enviromental Impact
Which of the following is not a fundamental of BIM?
- Visualization
- Quantification
- Communication
- Conversion
Check Answer
Conversion
Building Information Modeling MCQ (16-20)
What is full form of BIM?
- Building Internet Model
- Building Integrated Modeling
- Building Infrared Modeling
- Building Information Modeling
Check Answer
Building Information Modeling
Building Information Modelling (BIM) is used for
- Creating and managing data during design, construction and operation process
- Greater visibility and more sustainable option
- Cost saving on AEC projects
- All of the above
Check Answer
All of the above
BIM software is considered to be a(n) ______ modeling software.
- engineering
- mechanical
- 3D
- parametric
Check Answer
parametric
Which of the following information can not be generated using BIM?
- Topographical
- Spatial
- Elements
- Systems
Check Answer
Topographical
The appointment of a ______ is one of the initial steps in implementing BIM.
- BIM manager
- job captain
- lead architect
- chief drafter
Check Answer
BIM manager
Download Our App
“Vlcinfo” is an Educational App where you will be able to find details about various Job Related Updates, Test Series, Results, Syllabus, Old Papers, Video Lectures, MCQs Practice and much more.
App Features :
- Job Related Updates
- Test Series
- Video Lectures
- Study Materials
- Current Affairs
- Old Papers
- MCQs Practice
Civil Engineering MCQs
- Curves PYQs (Surveying) GPSC Civil Engineering 2024 Free
- 500+ Free AutoCAD Multiple Choice Questions
- 100+ Free Building Information Modeling MCQ Questions
- Surveying MCQ Questions And Answers – Civil Engineering
- 500+ Free Surveying MCQ Questions And Answers
- 100+ Free Highway Engineering MCQs, Civil Engineering
- 100+ Free Soil Mechanics Mcqs, Civil Engineering Mcqs
- 100+ Free Building Construction Mcqs, Civil Engineering Mcqs
- 100+ Free Building Materials Mcqs, Civil Engineering Mcqs
- 100+ Free Surveying MCQs, Civil Engineering MCQs
- 100+ Free Fluid Mechanics MCQs, Civil Engineering MCQs
- 1500+ Free GSSSB AAE Civil Engineering Mcqs Practice
- Fluid Mechanics Mcqs
- Solid Mechanics Mcqs
- Irrigation Engineering Mcqs
- RCC Mcqs
- Soil Mechanics Mcqs
- Highway Engineering Mcqs
- Hydrology Mcqs
- Surveying Mcqs
- Structural Analysis Mcqs
- Civil Engineering Mcqs With Practice Quiz
- Construction Planning and Management Mcqs
- Estimating, Costing and Valuation Mcqs
- AMC Sahayak Sub Inspector Paper Latest (Advt. No. 10-2017)